Hello everyone!
Our company is currently considering setting up standard guidelines for
Polyimide Board Rework & Repair. I have checked the latest IPCs (7711 &
7721), but neither give a clear cut answer to my questions. I was wondering
if maybe some of you could let me know what procedures you are following or
recommend.
Primarily, we want to know if preheating or baking out a board prior to
rework is required. If so, what temperature and for how long? (This is a
component loaded board, so we cannot exceed 85C). How long is considered
too long out of "dry" storage before another bake-out is required to drive
off any moisture absorption? And lastly, does anyone have any diffusion
coefficient data for different types of Conformal Coating (i.e. Conathane
CE-1175)?
Any information would be greatly appreciated.
Thank you!
Shala Burdette
##############################################################
TechNet Mail List provided as a free service by IPC using LISTSERV 1.8c
##############################################################
To subscribe/unsubscribe, send a message to [log in to unmask] with following text in
the body:
To subscribe: SUBSCRIBE TECHNET <your full name>
To unsubscribe: SIGNOFF TECHNET
##############################################################
Please visit IPC web site (http://www.ipc.org/html/forum.htm) for additional
information.
If you need assistance - contact Gayatri Sardeshpande at [log in to unmask] or
847-509-9700 ext.5365
##############################################################
|
|
|