Hi James,
Will WIP SMT PCBA run Wave Soldering afterwards? Will the PTH do Hand
Soldering afterwards? If yes, the long storage on work floor is not
appropriate. The PCB and components will absorb moisture and cause
components crack or PCB delamination during second reflow or wave
soldering or even hand soldering. Refer IPC J-STD-033A to control the
WIP.
B.R.
Wilson Poon
________________________________
From: TGAsia [mailto:[log in to unmask]] On Behalf Of James lee
Sent: Monday, April 20, 2009 4:25 PM
To: [log in to unmask]
Subject: [TGAsia] storage of PCBA WIP
Dear Friends,
One of our customer question our PCBA WIP management procedure since he
saw some of SMT / PTH subassemblies boards were keeping in production
area longer than 3 days,
Some of the boards are longer than one weeks and even a few pcs longer
than 1 month, so we had a big discussion about the shelf life of the
assembly boards but end of our discussion
It seems he was not convinced, hereby I need your help to let know is
there any IPC standards to describe this rule?
Thanks & Regards
James Lee
Legal Disclaimer:
The information contained in this message may be privileged and confidential. It is intended to be read only by the individual or entity to whom it is addressed or by their designee. If the reader of this message is not the intended recipient, you are on notice that any distribution of this message, in any form, is strictly prohibited. If you have received this message in error, please immediately notify the sender and delete or destroy any copy of this message
|
|
|