Yuan-chia Joyce Koo <[log in to unmask]>
Reply To:
TechNet E-Mail Forum <[log in to unmask]>, Yuan-chia Joyce Koo <[log in to unmask]>
Date:
Thu, 29 Nov 2018 12:52:46 -0500
Content-Type:
text/plain
Parts/Attachments:
text/plain (47 lines)
if my memory serve me right, the design authority is the program  
office who signed off the whole design package (that including SOW,  
contractual agreement, etc.etc.).  Program Mgr that oversee the whole  
design/reliability/compliances/legal issues (usually a company/or  
group of companies).  I remember many moons ago, our eng team got an  
request to change part to save money from one of the partners, the  
request were sent to program office and forward to engineering dept  
for assessment (temperature range issues)... it was hard fought until  
the requester realize it need put up full qual cost for the unit  
(since the change was not "equivalent or better" and key components/ 
material change, including PWB, etc. those were  consider as major  
change...  besides, the new temp range  proposed "eat" into the  
design margin... It was put into the rest once for all - at least  
once in my all work life in that company... many long distance conf   
call... the old days, internet was not that powerful).  Prog Mgr  
usually very careful  about changes, since it require his signature  
and his head  was on line)... IMHO.  Good luck and have a lots of  
mountain dew before you start "authority" process - a major  
challenges to keep good relationship with chaps on the  other end...
jk
On Nov 29, 2018, at 8:48 AM, Douglas Pauls wrote:

> Good afternoon all,
>
> A question for you.  The term "design authority" is used in some IPC
> specifications, such as J-STD-001.  Oddly enough, the term does not  
> appear
> in IPC-T-50.  So, I ask the group - if saw the term "design  
> authority" in a
> specification, what entity would that be to you?
>
> Secondly, the merger of United Technologies and Rockwell Collins was
> completed and yesterday was Day 1 for Collins Aerospace.  If any of  
> you are
> trying to contact a former Rockwell Collins employee, our domain  
> change.
> My new email is [log in to unmask]  Dave Hillman would be
> [log in to unmask] and so forth.
>
> If this question has shown up before, my apologies.  Been working on
> getting the domain changed on Technet and don't know if the previous
> attempts went through.
>
> Doug Pauls
> Principal Materials and Process Engineer
> Collins Aerospace

ATOM RSS1 RSS2