Mark,
The customer specifies requirements OR, depending on several factors, each
supplier lot shall be sectioned and analyzed. For re-qualification to 6012,
the requirements are specified therein.
Back in the good old days, when processes were not nearly as well managed
(nor could the be considering what some of us had to work with) and boards
were complex for the time, we would test small lot sizes. When a board type
was particularly difficult, a lot of one might comprise the it and would be
tested. Obviously, if one board out of a lot of one failed, only one lot was
rejected. There's a lot more to this story and some of the other old timers
can add interest to it.
MoonMan
---------------------------------------------------------------------------------
Technet Mail List provided as a free service by IPC using LISTSERV 1.8d
To unsubscribe, send a message to [log in to unmask] with following text in
the BODY (NOT the subject field): SIGNOFF Technet
To temporarily halt delivery of Technet send e-mail to [log in to unmask]: SET Technet NOMAIL
To receive ONE mailing per day of all the posts: send e-mail to [log in to unmask]: SET Technet Digest
Search previous postings at: www.ipc.org > On-Line Resources & Databases > E-mail Archives
Please visit IPC web site (http://www.ipc.org/html/forum.htm) for additional
information, or contact Keach Sasamori at [log in to unmask] or 847-509-9700 ext.5315
---------------------------------------------------------------------------------
|
|
|