Steve,
You stepped on a "hot button" issue at Hitachi. What we have been
doing is maintaining a controlled list of humidity sensitive parts and
performing a baking cycle on all of these parts prior to assembly. In
some cases, we keep a tight control (i.e. # of hrs) on exposure to
humid conditions and store the parts in a dry box. We have wanted to
eliminate this process for some time but have only managed to remove a
small number of parts from "the list". We are not willing to change
the environmental conditions in the plant due to ESD concerns.
This baking requirement places other limitations on our parts such as
requiring heat resistant trays and tubes (so no repackaging is
required for baking). It is a "royal pain". Also, our designers
rarely pick parts that are not sensitive or are even concerned about
the packaging issues for manufacturing (another sore spot for us
component engineers).
The real reason for our problems is that our Receiving Dept. insists
on opening all packages to perform a parts count prior to transfer to
Incoming Test (ah, beaurocracy at its best). We have worked with them
to properly seal the packages after counting so that we can stop doing
a majority of our baking. Also, we are using more dock-to-stock and
instructing Receiving to go by the outside labelling instead of
openning the packages. This also limits the problem considerably
(small wonder why we can't seem to get any REAL work done around
here).
My suggestion for you is to keep track of the unsealed time on your
parts and if it exceeds 2~5 days (your choice) then bake them for 12 ~
24 hours (also your choice) and then restart the clock. That way you
perform an extra process ONLY when necessary.
Regards,
Roger Held
Manager of Electrical Component Eng.
Hitachi Computer Products (America), Inc.
[log in to unmask] com
______________________________ Reply Separator _________________________________
Subject: Humidity Sensitive parts
Author: [log in to unmask] at Internet-HICAM-OK
Date: 5/9/96 3:18 PM
Hello out there.
We are looking into the handling of our humidity sensitive parts.
We currently keep them in their sealed bags, and reseal unused parts
immediately after a build(we build very low volumes of boards per day). We
are considering controlling the environment in the room where we build, and
keeping the humidity under 30% to eliminate any moisture build up in the
parts. Do I run into other problems, such as ESD issues, and how can I deal
with those? Are there health concerns from running in too dry an
environment? Any comments would be appreciated.
Thanks.
Steve Quinn
Heurikon Corp
|
|
|